Wastewater Treatment Plant Roof Replacement Phase II Completion
Daly City
Summary
The second phase of the treatment plant roof replacement is done and staff asked the board to formally sign off. The project ran about $86,000 over the original budget due to unexpected change orders, but stayed within the later approved total.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 26, 2026.
Impact analysis
The project's final cost was $1,960,774.04; formal acceptance carries no additional fiscal impact.
Ratepayers benefit from a protected treatment plant facility and a project finished within the approved budget.